There is a difference in implementing soft and mineral soil area.
Peat Soil
Flow
- A drains flow should be built initially to lower the water level for the peat soil condition in Malaysia which constantly traps water.
Type of drain | Measurement (m) |
Main | 1.5×1.2×1.2 |
Second | 1.2×0.9×0.9 |
Farm | 0.9×0.9×0.6 |
2. Excessive flow will increase the declining process which results in a continuous dry soil. Tree growth will be obstructed.
Cutting and Cleaning of Area
1.Done in the hot season, 3-4 months and the wood will dry out.
Road & Lane Construction
1. Large pieces of wood are being cut into 5m long, arranged vertically on suggested roads as a layer of support. Laterite is compressed into 10-20 cm thick on top of it.
2. Lanes are constructed from laterite layers 10-20 cm thick and 3-4 m wide.
Download Pineapple Farm Management Manual (Moris, Gandul, N 36, Josapine)(PDF)